PROJECT UPDATE || Melbourne Square Display Suite

IB Projects

10 Aug 2017


The external glazing is at 95% completion whilst the roofing has been completed. The building is locked up which has allowed for plastering works to commence, as well as services rough ins which are complete internally.

Curbs for the driveway and disability ramp have been completed and subgrade works for the asphalt road has commenced. Landscaping works are set to commence early next week with the large trees being installed.

Keep an eye on this space for further updates on this project.